New clinical-grade safety flooring for two treatment rooms at a dental practice in Chelsea, West London. The work was phased room by room so the practice never had to close, and the services were adapted to suit a new dental chair.
The practice needed the worn sheet flooring in two treatment rooms replaced with a hygienic, seamless finish, and one room prepared for a new dental chair. Closing the practice was not an option, so JAY Executions planned the works one room at a time, keeping the second surgery available for patients throughout.
Each room was cleared, the old floor was lifted and disposed of, and the subfloor was primed and levelled before a polyurethane-reinforced safety vinyl was laid with coved, capped skirtings and heat-welded seams. The result is a continuous, easy-to-clean surface that runs up the wall, as expected in clinical rooms.



Dental surgeries cannot simply shut for a refurbishment. Phasing the works room by room meant the practice kept one treatment room running while the other was being refloored.
Once the old floor was lifted, moisture readings showed high surface damp, and the cold, damp conditions stopped the levelling compound from curing. A damp-proof membrane was applied to both rooms before levelling, so the new floor is protected against moisture coming up from the slab.
Both rooms were measured on site in February 2024 and flooring samples were presented to the practice for colour and finish selection.
The scope and a room-by-room programme were agreed at the end of February 2024, so treatment could continue during the works.
Each room was stripped, protected against damp, levelled and refloored in turn, with the chair pipework adapted in the same visit.
Both treatment rooms were handed back ready for clinical use in March 2024.
The practice now has continuous, welded safety flooring in both treatment rooms, with coved skirtings that are quick to clean and a damp-proof layer beneath to protect the finish.
Because the work was phased, patients continued to be seen throughout. It is a typical example of how JAY Executions plans commercial and healthcare fit-out work around a business that has to stay open.