The Future Homes and Buildings Standards change the energy and ventilation parts of the Building Regulations in England from 24 March 2027. New homes will need to be designed around low-carbon heating and a better-performing building fabric. Projects whose initial Building Control documents go in before that date can stay on the current standards, but only if work on each building starts by 24 March 2028.
What this guide covers
What the Future Homes Standard is
On 24 March 2026 the government published its response to the Future Homes and Buildings Standards consultation, laid the amending regulations before Parliament and published new statutory guidance: new editions of Approved Document L (conservation of fuel and power) and Approved Document F (ventilation). The changes were announced to councils and building control bodies in Building Circular 01/2026.
“Future Homes Standard” is the name used for the new requirements for homes. The matching “Future Buildings Standard” covers non-domestic buildings. Both are delivered through the same amendments to the Building Regulations, so they are approved and inspected through Building Control in the normal way. This guide applies to England only.
The key dates and the transition rules
- 24 March 2027: the amended regulations come into force for building work that is not higher-risk.
- 24 September 2027: the start date for higher-risk building work and work to existing higher-risk buildings, which go through the Building Safety Regulator’s gateway process.
- 24 March 2028: the end of the 12-month transition period for non-higher-risk work.
In broad terms, the current standards continue to apply to a building where the initial Building Control documents (a full plans application, building notice or initial notice) were submitted before 24 March 2027 and work on that building starts before 24 March 2028. On a site with several buildings, the test is applied building by building, so starting the first plot does not protect the last one. The exact wording, and the separate rules for higher-risk buildings, are in the circular letter listed under sources.
Worth knowing: planning permission and Building Regulations are separate. A planning consent granted today does not fix which energy standard applies. That depends on when the Building Control documents go in and when work starts.
Who it affects
- Anyone building a new house, including self-builders and small developers.
- Owners converting a building into homes, for example offices, shops or barns into flats.
- Landlords and investors planning new-build or conversion schemes for rent.
- Developers and owners of new non-domestic buildings, under the Future Buildings Standard.
Some provisions also reach work to existing buildings, such as extensions, replacement windows and new heating systems. If you are doing that kind of work, ask your designer or Building Control which of the changes apply.
What it means for the design
The new Approved Document L sets tougher performance targets. In practice, for most new homes, that means:
- Low-carbon heating, typically a heat pump or a connection to a heat network, in place of a gas boiler.
- A better building fabric: more insulation, better windows and doors, fewer thermal bridges and better airtightness.
- On-site renewable generation, usually solar panels on the roof, in most cases.
- Ventilation designed alongside airtightness, under the new Approved Document F, so the home stays healthy as it gets tighter.
Each of these has knock-on effects for space, structure and cost. A heat pump needs an outdoor position and, usually, a hot water cylinder inside. Solar panels need a suitable roof area and a route for cables. All of it needs enough electrical supply capacity.
What needs to be done, step by step
- Decide which standard you are designing to. If you want to use the current standards, your Building Control documents must go in before 24 March 2027 and work on each building must start before 24 March 2028. Be realistic about whether the programme can meet both dates.
- Appoint an energy assessor at concept stage, not after the drawings are finished. The energy calculations should shape the design rather than check it at the end.
- Plan the plant. Find a place for the heat pump outdoor unit (thinking about noise, neighbours and access for maintenance), the cylinder, the ventilation equipment and the electrical consumer unit.
- Design the roof for solar. Check orientation, shading and roof structure, and allow a cable route to the inverter.
- Check the electricity supply early. Ask the network operator whether the existing connection is enough. Upgrades can take months.
- Detail the fabric: insulation thickness, wall build-ups, window specification, junction details and an airtightness strategy.
- Coordinate the M&E design with the architectural drawings, so the plant, ducts and pipework fit the spaces allowed for them.
- Write the standard into your contracts. State which version of the regulations the design and works must meet, and who carries the risk if the transition dates are missed.
- Test and certify at completion: airtightness testing, commissioning of the heating and ventilation, the energy certificates and the Building Control completion certificate.
Common problems and how to solve them
- No room for the cylinder or ventilation unit. Allow a plant cupboard on the first layout, not after the room sizes are fixed.
- The heat pump position does not work. Check noise, distance to boundaries and any planning conditions before committing to a location.
- The electrical supply is too small. Apply to the network operator as soon as the loads are known, and put the lead time into the programme.
- The design fails the energy calculation late on. Run the calculations at concept and again at technical design, and fix the fabric and services together.
- The transition dates are missed. If an older design will not start on site in time, budget for redesign rather than assuming the old standard still applies.
- Airtightness test fails. Agree an airtightness line on the drawings and inspect it before it is covered up.
Examples from our projects
On the conversion of a former high-street bank in West Ealing into a children’s activity centre, we coordinated the M&E design information, Building Regulations requirements and Part L documentation, including the energy calculation and EPC, so the project could move from concept to a buildable, compliant scheme. Read the case study.
Our guide to when M&E design should start explains why services need to be planned from the outset, which matters even more under the new standard.
Quick answers
When does the Future Homes Standard come into force?
The amended Building Regulations come into force in England on 24 March 2027 for building work that is not higher-risk, and on 24 September 2027 for higher-risk building work, subject to transitional provisions.
Can I still build to the current standards?
In broad terms, yes, if the initial Building Control documents for the building were submitted before 24 March 2027 and work on that building starts before 24 March 2028. Check the exact transitional provisions in Building Circular 01/2026.
Will new homes still be able to have gas boilers?
The new standard is designed to be met with low-carbon heating, typically a heat pump or a heat network connection, rather than gas boilers. Check the design with an energy assessor.
Does the Future Homes Standard apply to extensions?
The standard is aimed mainly at new homes, but some of the amendments also apply to work to existing buildings. Ask your designer or Building Control which provisions apply to your work.
Sources and further reading
- GOV.UK: The Future Homes and Buildings Standards, Building Circular 01/2026
- GOV.UK: Building Circular 01/2026, circular letter (dates and transitional arrangements)
- UK Parliament: written statement on the Future Homes and Buildings Standards, 24 March 2026
Want to go further? If you would like advice on your own property or project, or would like JAY Executions to design, manage or carry out the work, get in touch and we will look at your specific circumstances.
Important: general information only. This article is published to help readers understand the subject. It is not legal, regulatory, financial, technical or other professional advice, and it is not a substitute for advice on your own property or project. Rules, dates and figures can change after publication, so check the current official guidance before acting. JAY Executions Ltd accepts no responsibility or liability for any decision made or action taken in reliance on this article. Advice from JAY Executions is given only under a specific appointment for a specific project. Published November 2026.