Most commercial leases stop a tenant altering the premises without the landlord’s written consent. That consent is usually given in a Licence to Alter, normally a deed. Landlords and their surveyors will want drawings, a specification and evidence of the statutory approvals before they sign, so the information needs to be ready early to avoid holding up the fit-out.
What this guide covers
What a Licence to Alter is
A Licence to Alter is the landlord’s formal written consent to specific works to leased premises. It identifies the works, usually by reference to approved drawings and a specification, and sets the conditions the tenant must meet while carrying them out and at the end of the lease. It is normally drafted by the landlord’s solicitor and signed as a deed by both parties, and sometimes by a guarantor or a superior landlord.
When you need one
Start with the alterations clause in your lease. Leases generally do one of three things:
- Absolutely prohibit certain works, often anything structural or affecting the exterior. The landlord can simply say no.
- Allow works with consent, which is the usual position for internal fit-out works. This is when a Licence to Alter is needed.
- Allow some works without consent, commonly minor, non-structural internal works such as demountable partitions, sometimes on condition that the landlord is notified and given drawings afterwards.
If you are not sure which category your works fall into, take advice on the lease before work starts. Carrying out works without a required consent is a breach of the lease.
Can the landlord refuse?
Where the lease allows alterations with the landlord’s consent, section 19(2) of the Landlord and Tenant Act 1927 says that consent to improvements is not to be unreasonably withheld. Whether a work counts as an improvement is judged from the tenant’s point of view. The same section allows the landlord to require payment of a reasonable sum for any damage to, or reduction in value of, the premises, and its legal and other expenses. Where the improvement does not add to the letting value, the landlord can also reasonably require the premises to be reinstated.
Section 19(2) does not apply where the lease absolutely prohibits the works, and it sets no time limit for a decision. Some leases add their own terms, such as an obligation not to delay unreasonably. Read the lease with your solicitor.
Worth knowing: the landlord’s surveyor and solicitor will normally ask for an undertaking that you will pay their reasonable fees before they start reviewing. Budget for this alongside your own design fees.
What the landlord will ask to see
A complete, clear pack is the single biggest factor in getting consent quickly. A typical pack includes:
- Existing and proposed layout drawings, to scale, with the alterations clearly marked.
- A specification of materials and finishes, including anything fixed to the structure or the shell.
- Structural information: calculations and drawings for any openings, new loads, mezzanines or plant on the roof.
- Building services drawings: lighting, power, heating, ventilation and air conditioning, drainage, and any connections to the landlord’s systems.
- Fire safety information: how the works affect escape routes, compartmentation, the fire alarm and any sprinklers.
- A programme and method statement, including working hours, access, noise and deliveries in a multi-let building.
- Contractor details and insurance.
- Evidence of statutory approvals, or a commitment to obtain them: planning permission where needed, Building Regulations approval and any licences for the use.
What the licence usually says
- The works must be carried out in line with the approved drawings and specification, in a good and workmanlike manner and in compliance with the law.
- The works must be completed within a stated period.
- The tenant must provide copies of statutory approvals and certificates, and as-built drawings on completion.
- The landlord may require the premises to be reinstated at the end of the lease, with or without notice.
- The tenant is responsible for the landlord’s costs, and for insuring, or reimbursing the insurance cost of, the new works.
What needs to be done, step by step
- Read the alterations clause and confirm whether consent is needed.
- Survey the premises and record the existing layout and services. This is the baseline for the application and for any reinstatement later.
- Develop the design to the level the landlord will need: layouts, specification, structural and services drawings, and the fire strategy.
- Apply early, with a complete pack and a cover letter that lists every drawing and document.
- Run the statutory approvals in parallel: planning (if needed), Building Regulations and any licensing.
- Agree the licence wording, particularly the reinstatement obligation, through your solicitor.
- Start on site only once the licence is completed, unless the landlord has agreed in writing to an early start.
- Hand over the completion information: as-built drawings, certificates and the Building Control completion certificate.
Common problems and how to solve them
- An incomplete application. Each round of questions adds weeks. Send everything the landlord’s surveyor will need the first time.
- The design changes after consent. Variations to approved drawings usually need further approval. Fix the design before applying, and agree a process for minor changes.
- Connections to the landlord’s systems. Tie-ins to the fire alarm, sprinklers, risers or roof need the landlord’s engineers to agree them. Identify them early.
- Works started before the licence is signed. This is a breach of the lease and weakens your negotiating position. Plan the programme around the consent.
- No as-built record. Without accurate as-built drawings it is hard to show what changed, or to agree reinstatement later. Commission them as part of the works.
- A broad reinstatement clause. Negotiate it before signing, so you know what you may have to remove at the end of the lease.
Examples from our projects
For a two-floor restaurant in Islington that had already been fitted out, the landlord asked for drawings showing what had changed. We surveyed the premises and produced existing and as-built M&E drawings, with notes stating what had been retained and what had been changed, to support the operator’s Licence to Alter. Read the case study.
In West Ealing, we led the design and delivery of a former high-street bank’s conversion into a children’s activity centre, including structural alterations, M&E coordination and fire safety upgrades. Read the case study.
Quick answers
What is a Licence to Alter?
It is a landlord’s formal written consent, usually a deed, allowing a tenant to carry out specific works to leased premises, on conditions set out in the licence.
Can my landlord refuse consent to alterations?
If the lease absolutely prohibits the works, yes. If the lease allows them with consent and the works are improvements, section 19(2) of the Landlord and Tenant Act 1927 says consent is not to be unreasonably withheld, although the landlord can attach reasonable conditions.
What drawings does a landlord need for a Licence to Alter?
Typically existing and proposed layouts, a specification, structural and building services drawings, fire safety information, a programme, and evidence of planning and Building Regulations approvals where needed.
Do I need a Licence to Alter for minor works?
Not always. Many leases allow minor, non-structural internal works without consent, sometimes subject to notifying the landlord. Check the alterations clause in your lease.
Sources and further reading
Want to go further? If you would like advice on your own property or project, or would like JAY Executions to design, manage or carry out the work, get in touch and we will look at your specific circumstances.
Important: general information only. This article is published to help readers understand the subject. It is not legal, regulatory, financial, technical or other professional advice, and it is not a substitute for advice on your own property or project. Rules, dates and figures can change after publication, so check the current official guidance before acting. JAY Executions Ltd accepts no responsibility or liability for any decision made or action taken in reliance on this article. Advice from JAY Executions is given only under a specific appointment for a specific project. Published November 2026.